1) SURFACE CLEANING
2)Fire fighting line
3)Electrical work
4)HACKING ON RCC SURFACE OR BONDIT APPLICATION IS DONE OR NOT
5) ALL MIVAN WALL TIE HOLES ARE PROPERLY CLEAN AND REFILL WITH THE HELP OF MICRO-CONCRETE
6)TIE ROD HOLES ARE CLOSED PROPERLY
SURFACE CLEANING :
It's process in which all floor should be clean loose material to be remove first .
Any type of breaking is required kindly do this no priority.
FIRE FIGHTING:
In this form to ensure first all Fire concealed line to be done then start gypsum activity
ELECTRICAL WORK:
ALL CONDUIT AND BOX FIXING WORK TO BE DONE WITHOUT FAIL FILL THE GROVE AFTER CONDUITING WTH THE HELP OF CEMENT MORTAR AND APPLY FIBRE MESH OVER IT TO AVOID CHANCES OF CRACKS
BONDIT ON RCC:
On rcc surface need to be apply 1coat of bondit chemical on all rcc surface for bonding agent
Wall tie:
Remove all pvc sleeve from rcc and fill it with micro Grout chemical .
TIE ROD HOLES:
To ensure all TIE rod HOLES to be filled properly.
Methodology of gypsum :
1)After all preparation start right angle of flat or that floor
2) ensure thickness of gypsum ,ceiling or Wall area .
3) ensure any plaster required on extra thickness .
4) Apply fibre mesh on required area .
5) check gypsum material date ,setting time quality.
6) after the final level pads checking start gypsum punning on ceiling and then Wall area check any gap between this or cracks found on it
7) ensure beam levels , Wall side Dhar are in plumb or sharp edge .
8) line ,level plumb to be check simultaneously during work .
9) after the final work area is To be clean or not ensure first .