STEP2: LAYOUT OF DPC, along with the architect dwg ,check right angle, plumb, sizes of room , openings as specified on dwg .
STEP3: Start block work above Dpc check level during laying of block ,plumb Should be check, minimum thickness of joining mortar
STEP4: After 4 layers of block work cast coping on it for sustain the load .
STEP5: After the casting of coping complete the above block work on it .
STEP6: Top layer of block work Should be filled with mortar properly and metal fix on it to avoid cracks on joints .
STEP7 : To fix door frame or jamb simultaneously during the work .