SLAB CYCLE
1st DAY :
1.1 Level Shifting and grid line point mark on slab
1.2 Wooden templates /thesi work at 300mm c/c for mivan vertical panel
1.3 Reinforcement binding work of column ,shear wall, Non structural wall
1.4 Deshuttering of wall panel
1.5 Outside top panel removing for bracket fixing - safety net fixing
2nd Day :
2.1 Complection of R/F column
2.2 Vertical wall panel fixing internal
2.3 External Bracket Fixing
2.4 Deshuttering & shuttering of beam and deck soffit of slab
2.5 cutting & bending of beam & slab R/F
2.6 External Bracket Fixing & safety net fixing
3rd Day:
3.1 Complection of R/F column
3.2 Vertical wall panel fixing internal
3.3 External Bracket Fixing
3.4 Deshuttering & shuttering of beam and deck soffit of slab
3.5 cutting & bending of beam & slab R/F
3.6 External Bracket Fixing & safety net fixing
4th Day:
4.1 Shuttering Complection of Beam & Slab
4.2 Start R/F Binding Work Of Beam
5th Day:
5.1 Shuttering Complection of Beam & Slab
5.2 Start R/F Binding Work Of Beam
5.3 checking of Deck Formwork levels
5.4 R/F Binding Work of beam Complection & start R/F OF SLAB
5.5 Shuttering of External Wall Panel
6th Day:
6.1 R/F Binding Work Of slab
6.2 Kicker & Sunken Fixing Supporting Work
6.3 Electrical Conduiting & servicess Sleeves baem / Slab
6.4 Gridline Checking ,verticality Checking using plumbob
7th Day:
7.1 R/F Binding Work Of slab complection
7.2 Kicker & Sunken Fixing Supporting Work complection & checking
7.3 Electrical Conduiting & servicess Sleeves baem / Slab complection
7.4 Gridline Checking ,verticality Checking using plumbob
8th Day:
slab casting